As anticipated, the delivery of heavy timbers arrived this week and installation work has begun. This week’s image gallery displays heavy timber work, flooring, walls and roof work. Additionally, plumbing rough-in has been completed in the take out building and will move to the Sandbar and kitchen area.

Interior wall framing is underway in the new restaurant area, including restrooms.

Week 8 pictures may be viewed on the Foundation website by clicking the Members tab and choosing Photo Gallery or by clicking the picture above.